The total project budget is $22.5 million, with a significant amount of that budget to be spent on accessibility improvements (to address compliance with the Americans with Disabilities Act, or ADA) along with safety and security upgrades.
Proposed major changes include:
- new, secure front entry vestibule;
- new elevator;
- bathroom upgrades throughout the building;
- removal of carpet;
- relocation of the playground;
- window replacements; and
- traffic flow changes around the building, including a "bus loop" in the front of the building.
A proposed site plan and renderings of the front of the building are included in the presentation, along with a more detailed list of interior improvements.
The PTO Executive Board previously submitted comments on the initial proposed plans (originally presented at our January 19 meeting).
Do you have additional comments or questions about the proposed plans for the building? Please send comments to [email protected] and we will share them with the Facilities Department.